The Deadline Approaches - LEED Platinum Home Progress Report

Contractor’s Notes 6-27-11

Hello Everyone,

For this week on site:

The carpenters are trimming out the first floor (the 2nd is complete).

Tiles are being laid.

Electrical and plumbing fixtures are being installed.

The alarm company is complete.

Paint is going on the walls and ceilings.

Cabinets are getting installed.

At the end of the week, the floors are getting refinished.

The marble slabs for the showers have been delivered so the shower door templater is coming out Wednesday to measure.

The weekly meeting has been moved to Thursday morning at 7am. Barbara and Phyllis, you can come anytime on Wednesday to take pictures.

The excavator is installing the layers that Josy and LEED requested for the permeable driveway.

B&D mentioned that they did put the anti-termite mesh over the vents. One of the B&D guys can direct you so that you can get a picture.

The Paperstone countertop should be here by the end of the week.

The only subs who may be working on the 4th are the floor refinishers or painters. We have asked that all big trucks stay off site and to keep the noise down due to the holiday celebration at Tilley Pond.

Anthia, please keep the appliance delivery for July 6th.